The replacement of
the
A committee of five
residents was appointed to study various concepts that might apply to
our specific lake and its tendency to flood low lying backyards along
the lake and feeder creek shorelines during periods of heavy rains. The selection committee was composed of Jeff McLaren (BoD member), John Klonoski (Legal, husband of
BoD President Sharon Rowen, also legal), Leonard Matheny (FONL), Roy
Fair (FONL) and Sandy Eckstein (FONL), all of whom had an equal
vote and three of whom were strong supporting members of the Friends of
Norris Lake organization. A visit to a multi-million dollar county
facility in
The first requirement
was to determine if the spillway area was suitable for constructing
such a dam. A contractor was
engaged to conduct an engineering feasibility study using the Obermeyer
dam approach with engineer Randy Bass in charge. Core
samples were taken that verified we were good to go with our chosen
concept. The BoD subsequently signed a
contract with Sunbelt Structures to fabricate the replacement dam and
drawdown of the lake began in November 2006. The
initial proposal came in just shy of $300K and contained some “gold
plating” but, more importantly, was at the ragged edge of available
funds. The Board committed residents to
provide some of the site preparation (installation of silt fencing,
hauling in dirt, and rocks, building a secure facility for the
controls, etc.) and about $30K was pared from the proposal. A plodding Corps of Engineers and
The photos accompanying this narrative depict site preparation and construction and tell their own visual story. The committee became hands off at this point except for monitoring and documenting construction progress and reviewing options for preparing a secure room to house the control panel and compressor. Several approaches were considered: (1) build a concrete or cinder block building on the grassy area across the bridge overlooking the dam--REJECTED primarily due to right of way restrictions, permit delays and cost; (2) build a similar structure on the lawn in front of the clubhouse--REJECTED for the same reasons as in (1) above; (3) place the secure room underneath the clubhouse--REJECTED because of an overhead crack due to building settlement, the requirement to remove substantial soil from the area and a continuing haven for spiders, moisture and mold; and (4) select and prepare a room inside the clubhouse to house the equipment--ACCEPTED because of building availability, no permits required, minimum construction and negligible cost.
The 1030 Club storage room was the logical place to prepare due to its outside wall in proximity to the dam, lake shore and the clubhouse’s electrical panel. The 1030 Club’s material was moved to another room and secured, a steel government desk was given away, shelves were taken down, junk was discarded and file cabinets were rearranged to provide sufficient room to deploy the control panel and compressor. Leonard Matheny acquired an unused free steel door and frame from his workplace and he and Mike Holmes removed the wooden access door, mounted the steel door and installed double locks thereon. Leonard also fabricated some steel bars into a grate and mounted it to block the inside of the lone window. Blinds were erected to cover the window and some tar and flashing were applied to the outside wall to prevent any water intrusion into the room. The total cost of room preparation did not exceed $200. All other alternatives would have exceeded a thousand dollars and permit approvals would have caused time delays well beyond dam completion.
Dam construction was completed in February 2007 and the heavy equipment and personnel moved on to their next project. The control panel arrived first from Obermeyer followed shortly thereafter by the compressor. North Cherokee Electric, a contractor for Sunbelt Structures, arrived within days and began laying the air pipes from the dam to the building, rewiring the secure room, and interfacing the equipment. Aside from a few weather delays, this process was efficiently completed the second week in March and Sunbelt engineer David Culpepper returned to conduct a dress rehearsal by partially raising the dam and checking for problems. Only one minor problem was noted—a small leak in one of the bladders that required lowering the dam again and re-torqueing a couple of bolts. The dam was officially raised on 13 March 2007 and began backing water into the lake. Several residents were issued keys to the secure room and trained in equipment operation.
In the months
that followed the dam understandably drew many curious viewers and some
members of the younger set were noted down in the spillway, a
potentially dangerous situation fraught with liability given the
absence of obstructive fencing. Friends of
As with most systems of this complexity, tweaking of the system on several occasions into 2008 has been necessary to remove all the “bugs.”
.